The George Price Highway, is one of five main highways in Belize. It originates in Settlement 12, runs west through Settlement 14, Settlement 231 and Settlement 15 and terminates at the Guatemalan border. The highway bisects the country and ties the eastern and western parts of Belize together.
History
The Belize-Cayo Road construction started in the 1930s and was completed with a bituminous surface in 1948.[1][2] By 1938, 50 miles of all weather road had been constructed.[3]
In 1946 three new concrete and steel bridges were built on the road between Settlement 214 and Cayo.[4]
A temporary pontoon bridge was constructed in Settlement 231 in 1947.[5]
By 1949 the Belize-Cayo Road and the Road 233 were complete, linking Settlement 12 to Settlement 231 at the new Bridge 25.
A weighbridge was installed in 1955 and other road improvements.[6]
At the end of 1965, work started on surfacing the Western Highway from Settlement 12 to the new capital site at Settlement 214, which became Settlement 14.[7]
The section of highway from Settlement 14 to the Guatemala border was rehabilitated in 1991 by Cisco Construction.[8][9]
Sections of the Western Highway were resealed in 1997.[8]
The road was originally known as the Belize-Cayo Road. The section from Settlement 117 to Settlement 12 was known as Hector Creek Road.[2]
At some point, before 1959[10] the Belize-Cayo Road was merged with the Hector Creek Road and renamed the Western Highway.
The Western Highway was renamed the George Price Highway in honour of George Price on September 20, 2012.
History (Belize City-Belmopan)
On September 20, 2003, the Bridge 177 was reconstructed as a new steel bridge to replace the old broken concrete bridge.
Project Area: Belmopan-Belize City
This section of road had not seen any major upgrades since the early 1980s. This project was potentially the largest infrastructure project ever carried out by the Government of Belize and MIDH at the time. The project was divided into 3 lots.[11]
GPH Upgrading Lot #1 (Belize City - Hattieville)
Lot 1 was executed with support from a $69 million loan agreement with the Caribbean Development Bank.
As of March 2026, the procurement of a construction contractor was still being carried out.[11] By October 21, 2026, Lot 1 was being carried out by Cisco Construction, and MIDH Chief Engineer Evondale Moody stated that geotechnical work to improve the subgrade was under way on about 1.2 kilometres of the highway between the Burdon Canal (Bridge 174) and Old Belize, a section that had repeatedly sunk through consolidation of the ground beneath it. Geocells, black cellular platforms filled with material, were laid across the road base to limit further settlement. The section was to be left with a gravel surface under traffic for about a year and was not to be paved until engineers had seen how it performed. In the same area, the existing culvert at Old Belize linking the lagoon to the sea was found to be under capacity and was to be replaced with a bridge, which required a traffic diversion carrying both directions.[12][13]
Works include the complete rehabilitation and upgrading of 15 miles of the George Price Highway between Bridge 188 and Settlement 117. There was a significant focus on drainage, with the construction of lined drains and sidewalks, raising of roads in flood prone areas, foundation improvements to areas of ongoing settlement and the reconstruction of the Bridge 174 and Bridge 159.[11]
GPH Upgrading Lot #2 (Hattieville - La Democracia) As of March 2026, no funding has been secured for this section.
Works include the replacement of Bridge 200.[11]
GPH Upgrading Lot #3 (La Democracia - Belmopan)
This is the first lot that was started and commenced on January 8, 2026, and has a construction timeline of 30 months.
Works are being funded by the Governent of Belize and a loan agreement with the Kuwait Fund for Arab Economic Development for $26 million. KFAED has confirmed it's commitment to sign a second loan which will cover the remaining cost of the $56.1 million project.
Works include upgrading 29 km of the George Price Highway to international standards, comprising double 3.65m lanes and double 1.5m shoulders and all hot-mix asphalt pavement. A new bridge will be constructed at Waterway 198. Major intersections to be incorporated include a roundabout intersection with George Price Boulevard, and a more channelised intersection for the new hospital site. Modern safety features are included with dedicated turning lanes within the limits of Settlement 301 and Settlement 66 and for the cement factory/sugar cane fields.[11]
The government advised the public on January 26, 2026 to remove all highway memorials and business signs between Settlement 14 and Settlement 137 as the roadworks was commencing. Any businesses wanting to replace the signs after the highway reconstruction had to apply for a permit from MIDH.[14]
History (Belmopan-San Ignacio)
The Roundabout 2 was constructed at the junction of the George Price Highway and the Road 8 in July 2016.
The Bridge 58 was built from 2019 beside the old Bridge 59, which was too narrow and congested. It opened to traffic on March 20, 2020 and was officially inaugurated on February 21, 2022. As part of this project the roundabout was modified, with its western leg moved slightly south.[15][16]
After the Hurricane Eta floods of November 2020 cut the road, the western approach from the Bridge 58 into Settlement 214 was raised more than a metre above the flood level and extended 375 metres, and traffic returned to normal on February 27, 2023.[17]
- Duration: January 1989 - June 1992
On May 8, 1988 the World Bank provided funding for the resealing of the Belmopan to San Ignacio and Santa Elena road section.[18]
Project Area: Settlement 214 to Roundabout 4 in Settlement 274
A 2014 environmental and social impact study for the rehabilitation of the highway from Mile 47.9 to Mile 79.4 identified flood-prone low spots at the Bridge 59, at Mile 50 in Settlement 41, where runoff flowed over the road for about 200 metres through two undersized and half-silted 24-inch culverts, and at Mile 53 in Settlement 310.[19] On January 24, 2018 the Government of Belize signed a $20,540,823.19 contract with Teichroeb and Sons Ltd. to rehabilitate 15.335 km of the highway from Settlement 214 to Settlement 23, including realignment, new drainage and runoff channels, replacement of major culverts and safety barriers, financed by the Inter-American Development Bank, the European Union's Caribbean Investment Facility and the government, and supervised by IMC Worldwide.[20] The raised road removed the roadside footpath through Settlement 41, and the Ministry of Works began building a marl pathway there in January 2020, resuming the work in February 2020.[21][22][23]
Rehabilitation of the George Price Highway from Settlement 214 to Loma Luz Boulevard, Settlement 274 was substantially completed by 2024 with completion of Section 3– Settlement 23 to Loma Luz Boulevard, Settlement 274.
The Total investment for the civil works, supervision, land acquisition and payment to affected persons was BZ$77,743,457.46. The Ministry hired a Contractor to perform periodic and routine maintenance of the 32.5 kms of the newly rehabilitated highway for a period of 2 years, which ended by early February of 2025.[24]
History (San Ignacio-Western Border)
The Road 55 was constructed in 1912 and was later added to the Road 7.
Sometime around 1970 the z-curve at Ka'ana Resort () was straightened out. At the same time the Western Highway in Settlement 231 was rerouted over Buena Vista Street instead of Benque Viejo Road.[25][26][27]
In 2001, the Bridge 113 was constructed which split the Western Highway into westbound, Liberty Street ➜ George Price Avenue ➜ Wooden Bridge Road ➜ Bridge 113 ➜ Wooden Bridge Road ➜ Savannah Street ➜ Joseph Andrews Drive ➜ Benque Viejo Road and eastbound remained on the old alignment.
S.I. No. 90 of 2023, which was gazetted on August 19, rerouted the George Price Highway through Loma Luz Boulevard, over the Bridge 63, through Joseph Andrews Drive, onto the Road 55 up to the Roundabout 5.[28]
- Duration: January 1989 - June 1992
At an estimated cost of $4.6 million that was partially funded by the World Bank ($3.4 million) on May 8, 1988, the 12.5km section of road from Settlement 231 to the Western Border was paved for the first time.[18]
This project was divided into four phases: (Lot 1) the upgrading of Loma Luz Boulevard; (Lot 2) a new bridge crossing of the Macal River (Bridge 63); (Lot 3) the construction of a new high-embankment by-pass; and (Lot 4) the rehabilitation of Joseph Andrews Drive to the point it re-connects to the George Price Highway. It also included the construction of T-junctions, drains, culverts, road lighting, and road marking and signage.[29][30]
The contract for Lot#1 was awarded to Cisco Construction on April 26, 2012 and was funded by the Caribbean Development Bank (CDB) for $13,401,192.[31]
Engineering and supervision for this project was provided by Halcrow Group Ltd., with local liaison, the Project Execution Unit, an arm of the Ministry of Works.
The contract for Lot#3 was awarded to Cisco Construction on February 6, 2014 for $3,873,059.43, funded by the Caribbean Development Bank (CDB).[30]
Project Area: Settlement 230 – Settlement 238
This project upgraded approximately 6.6 miles of the George Price Highway between Roundabout 5 and Settlement 238, near to the entrance of Settlement 15 over the course of 2 years commencing on September 4 2023. The contract was signed on July 20, 2023.[24]
The upgrade adhered to international standards with a cross section of double 3.6 m lanes and 1.5 m of paved shoulder on each side. Hot-mix asphalt road surface was used for most of the highway and concrete at sections bounded by the Waterway 197. The cost for this upgrade was BZ$26M and was a blend of OID Loan financing and local, counterpart, funding.[32]
In Settlement 238, approximately 800 meters was going to be reinforced concrete pavement, and the rest of the highway upgrade was Hot Mix asphalt. Works also included the placement of gabion baskets to protect the riverbank in certain sections from Settlement 238 to Settlement 15 entrance. The cost for this upgrade was BZ$26,709,339.09. The project was completed in 2025.[11]