History

On December 19, 2017 the Government of Belize signed an $11.3 million contract with M&M Engineering to build a new Roaring Creek Bridge at mile 48 of the Road 7, with its approaches and drainage over a length of 485 metres, under the supervision of IMC Worldwide, replacing the old Bridge 59.[1] The bridge stood twelve feet higher than the old one, with two lanes and two pedestrian paths. It opened to traffic on March 20, 2020, and Prime Minister John Briceño officially inaugurated it on February 21, 2022, together with 32.5 km of the rehabilitated George Price Highway.[2][3]

In November 2020 the Hurricane Eta floods reached the western approach.[4] The Ministry of Infrastructure Development and Housing then raised that approach more than a metre above the flood level and extended it by 375 metres for $2,260,000. During the works, traffic was diverted through village streets and over the old bridge, and normal flow resumed on February 27, 2023.[5]