D908
Chiquibul Road
Cayo
Loading map...
Constructed
1955 (71 years ago)

Table of Contents

History

The Chiquibul Road was constructed by the Forest Department in 1954 at a cost of $1,500.00 per mile and completed by 1959.[1]

Etymology

In the 2013 Ministry of Works file the road is named Caracol Road and starts at the Tripartite Junction close to Settlement 90 and ends at Caracol Archaeological Reserve.[2]

Phase 1 – Caracol Road Upgrading Project

The Caracol Road Upgrading Project was funded by the Government of Belize and the OPEC Fund for International Development, through a US $40 million loan. Works commenced in February 2020 and were completed in 2022.[3]

Phase 1 is approximately 34.7 km (21.5 miles) and divided into three lots. The project included the construction of earthen embankments, crushed gravel pavements, and two (3.65m) lanes with (1 m) shoulders with a double bituminous chip-seal wearing course. The road drainage scheme was also upgraded through the replacement of undersized culverts and the upgrading in some cases to reinforced concrete box structures. The road segment was completed with modern ancillary road safety features, including high visibility road signs, edge markers, lane markings, and safety rails.

Lot 1A - (Georgeville – Tripartite / Santa Elena – Cristo Rey / San Antonio – Tripartite)

Lot 1A was 26 km in length, from the George Price Highway / Georgeville intersection to the Tripartite Intersection and from the intersection with Road 7 in Settlement 274 to the Tripartite Intersection. The project duration was 30 months, reflecting completion in August 2022 at a contract price of Bz$37,988,176.55.

Lot 1B (Tripartite Intersection - Blancaneaux Lodge Line)

Lot 1B was 8.8km in length, was completed as of the end of November 2021. The defects correction period closed November 2022. The final contract value was Bz$14,898,164.44.

Lot 1C (Blancaneaux Lodge Line – Pinol Line)

Lot 1C was 7.25 km in length, through the Mountain Pine Ridge Forest Reserve. The road section was modified slightly to 3.35m lanes and 0.5m shoulders; this was done prior to contract award to Belize Roadway Construction Ltd., on 21 May 2021, as a cost savings exercise. Three new bridges were constructed within the road segment. The bridges being...

The project commenced on 2 August 2021 with a contract period of 18 months, reflecting completion on 2 February 2023. An extension of time was given to 2 July 2023, due to excavation in rock, which was unforeseen and the effects of several severe weather events. At the end of February 2023, the entire section was at the level of first coat chip seal. At that time the bridges at Waterway 236 and Waterway 213 were completed with the concreting of the triple span Bridge 69 deck the remaining activity for the construction of bridges.

Lot 1C, and by extension, Phase 1 of the Caracol Road Upgrading Project was completed by mid-June at an approximate cost of Bz$16,402,152.12[4]

Phase 2 - Caracol Road Upgrading Project

The Caracol Road Upgrading Project – Phase 2 covers the distance from Pinol Line to the Caracol Archaeological Site, a distance of 42.9km (26.2 miles), which passes through Douglas da Silva camp. Phase 2 is divided into three lots. Lot 2A (23.7km) from Pinol Line to Guacamallo Bridge. Lot 2B the construction of Bridge 108 and Lot 2C (18.7km) from Guacamallo Bridge to Caracol Archaeological Site.

Construction contracts were signed with CISCO Construction in April 2022. The main construction camp was set up at Douglas da Silva camp. Road setting out and clearing was ongoing in 2024.

Progress was slow and the contractor fell 4 months behind schedule. The MIDH wrote to the contractor and held meetings with the supervision team to instruct that every measure be taken to get the works back on program. The contractor’s construction management team was re-organized in response to the Ministry’s intervention; improvements in production was noticed almost immediately. Despite a comprehensive review, the project’s rate of progress suffered real and difficult-to-overcome setbacks. These included: the isolated location, difficult and wet terrain, limitations in working in nature reserves, shortage of human resources, countrywide shortage of dynamite, and bitumen and a proliferation of natural underground springs.[4][5]

The Chiquibul Road was completely paved by the end of 2025.[6][3]


Bridges

#
1Barton Creek Bridge
CY
Barton Creek
2021
-
8.7
5
concrete
paved
87
1,428,180,552
2Barton Creek Bridge
CY
Barton Creek
-
2020
5
-
wood
wood
87
-
3First Creek Bridge
CY
First Creek
2025
-
21.4
-
concrete
paved
529
-
4First Creek Bridge
CY
First Creek
1955
https://edepot.wur.nl/484832
12
-
concrete
concrete
529
-
5Guacamallo Bridge
CY
Macal River
2025
-
130.7
11
concrete
paved
368
-
6Guacamallo Bridge
CY
Macal River
1957
2025
76
1
concrete
concrete
358
-
7Mahogany Creek Bridge
CY
Mahogany Creek
1955
https://edepot.wur.nl/484832
8.8
-
concrete
concrete
501
-
8Mahogany Creek Bridge
CY
Mahogany Creek
2025
-
-
-
concrete
paved
501
-
9Mollejon Bridge
CY
Mollejon Creek
1955
https://edepot.wur.nl/484832
18
-
concrete
concrete
437
-
10Mollejon Bridge
CY
Mollejon Creek
2025
-
20
-
concrete
paved
437
-
11Mollejon Tributary Bridge
CY
Mollejon Tributary Creek
1955
https://edepot.wur.nl/484832
12
-
concrete
concrete
440
-
12Mollejon Tributary Bridge
CY
Mollejon Tributary Creek
2025
-
14
-
concrete
paved
441
-
13Oak Burn Bridge
CY
Oak Burn
1955
https://edepot.wur.nl/484832
23
-
concrete
concrete
442
1,428,197,542
14Oak Burn Bridge
CY
Oak Burn
2022
-
35.3
8.1
concrete
paved
444
1,428,197,541
15Pinol Creek Bridge
CY
Pinol Creek
1955
https://edepot.wur.nl/484832
25
-
concrete
concrete
407
1,428,198,676
16Pinol Creek Bridge
CY
Pinol Creek
2023
-
89.2
-
concrete
paved
411
1,428,198,675
17Privassion Bridge
CY
Privassion Creek
1955
https://edepot.wur.nl/484832
21
-
concrete
concrete
451
1,428,198,339
18Privassion Bridge
CY
Privassion Creek
2022
-
23
15
concrete
paved
453
1,428,198,338
19Rio Frio Bridge
CY
Rio Frio
1955
2025
13
-
concrete
concrete
460
-
20Rio Frio Bridge
CY
Rio Frio
2025
-
15
-
concrete
paved
460
-
21Rio On Bridge
CY
Rio On
1955
https://edepot.wur.nl/484832
60.4
1
concrete
concrete
442
-
22Rio On Bridge
CY
Rio On
2025
-
63
-
concrete
paved
442
-
23Rio On Bridge
CY
Rio On
2025
-
65
1
concrete
concrete
442
-
24Vaqueros Creek Bridge
CY
Vaqueros Creek
2025
-
23.6
-
concrete
paved
536
-
25Vaqueros Creek Bridge
CY
Vaqueros Creek
1955
https://edepot.wur.nl/484832
8.6
-
concrete
concrete
535
-