The Hummingbird Highway, alternatively known as Route AR3 in the internal highway numbering system, is one of the four major highways in Belize. It traverses the Stann Creek Valley from the Roundabout 9 in Settlement 79 through the Maya Mountains and ends at the Roundabout 2 in Settlement 14.[1] It connects the Road 7, to the Road 5 6 miles outside of Settlement 79. It partially follows, and sometimes uses the infrastructure of the former Stann Creek Railway.
History
On August 16, 1949 the Survey Department began a reconnaissance survey for a road from Roaring Creek, on the Belize–Cayo road, to Middlesex in the Stann Creek Valley.[2] On January 14, 1950 the Gazette published the Director of Public Works' application to have the survey line proclaimed a public road, with a reserve of fifty feet on each side. The first section ran about 14 miles from Roaring Creek to Caves River, through Orange Walk, Roaring Creek works, Caves works and St. Hermans.[3] The reconnaissance was completed by mid-1950 with a route of 32½ miles located, and the Public Works Department began construction on February 6, 1950 as a Colonial Development and Welfare project. The survey work ended on June 30, 1951.[4][2]
Construction was completed on March 31, 1954 at a cost of $2,083,537, and Governor P. M. Renison opened the road to traffic on April 3, 1954.[2][5] The new road linked Belize, Cayo and the north of the colony by road for the first time with the Stann Creek Valley, the centre of the citrus industry.[6]
The road was financed by Great Britain as a Colonial Development and Welfare grant. At each end of the road a board was erected that read: "ROARING CREEK---MIDDLESEX ROAD. KNOWN AS THE HUMMING BIRD HIGHWAY.
PRESENTED TO THE PEOPLE OF BRITISH HONDURAS BY THE PEOPLE OF GREAT BRITAIN.
SURVEYED BY THE SURVEY DEPARTMENT FROM 16. 8. 49 TO 30 .6. 51.
CONSTRUCTED BY THE PUBLIC WORKS DEPARTMENT FROM 6. 2. 50 TO 31. 3. 54.
COST $2,083,537. LENGTH 32½ MILES
OPENED TO TRAFFIC BY HIS EXCELLENCY THE GOVERNOR P. M. RENISON, ESQ., C.M.G., ON THE 3rd APRIL, 1954. "
The board at the Middlesex end was the same except that it began with MIDDLESEX---ROARING CREEK ROAD[7]
In 2002 the western approach to the Sibun Bridge was washed away from floods.[8]
A massive flood event happened on June 11, 2026. The Waterway 208 flooded the road at the Southern Regional Hospital, at mile 7 between Xaibel Gas Station and Road 70, and on the west side of Settlement 120.[9] And then on June 24 the road collapsed over Waterway 28 which was immediately repaired.[10]
This highway has always been called the Hummingbird Highway.[11]
In October 1988 the Commission of the European Communities (CEC) signed an agreement with the Government of Belize within the terms of the Lome Convention III to provide funding for the Improvement of the Hummingbird Highway.[12][13]
Cisco Construction was given the initial contract and did such a good job that on March 17, 1998 they were given a second contract to complete the remaining 10 miles from the Bridge 30 to Roundabout 12. The total cost of the second contract was $20.5 million with the government providing 3.5 million, and the rest coming in the form of a loan from the Caribbean Development Bank.[14]
- Project Area: Roundabout 9 to Roundabout 12
- Duration: 2015-2018
- Cost: $75.1 million
This project rehabilitated 55 miles of the Hummingbird Highway and was financed by the Kuwait Fund for Arab Economic Development ($27 million) and OFID ($24 million) with the remainder being covered by the Government of Belize.[15]
The project replaced 8 single lane bridges with box culverts and new bridges and straightened a lot of curves.[16]